Dedicated Server Migration Without Downtime

Blog 2 min read

Migrate a dedicated server with no visible downtime: copy time, new IP, firewall and rDNS, parallel run, cutover and a rollback you can use.

A dedicated server migration differs from a cloud move in three ways: the new machine has a new IP address, copying hundreds of gigabytes takes real time, and hardware details such as disks and remote management must be set up from scratch. The sequence below keeps the old server serving until the new one has been tested.

Before you order the new server

  • List software versions, services, cron jobs, firewall rules, IP-based allowlists and reverse DNS entries.
  • Measure the data size. On a fully used 1 Gbit/s link one terabyte takes about two and a quarter hours in theory; plan for several times that.
  • Decide the disk layout and RAID level for the new machine.

Runbook

  1. Install and secure. Operating system, SSH keys, firewall, updates. See the first 24 hours.
  2. Lower the DNS TTL a day before the cutover.
  3. Initial copy. rsync the data and load the database while the old server keeps serving.
  4. Test on the new IP. Use the hosts file, run login, checkout and background jobs.
  5. Update IP-bound items. Firewall allowlists at partners, payment provider callbacks, mail server reverse DNS and SPF if the sending IP changes.
  6. Freeze and final copy. Pause writes briefly, repeat the sync and the database copy.
  7. Switch DNS. Change A and AAAA records and watch both servers’ logs.
  8. Parallel run. Keep the old server online one to two days, with its cron jobs stopped.
  9. Decommission. Wipe disks securely before the old hardware is returned or reused.

What is special about dedicated hardware

ItemWhy it matters
New IP addressEverything bound to the old IP must be updated
Reverse DNS and mailA new sending IP needs rDNS and a matching SPF record
Remote managementSet it up and secure it before you need it
Disks and RAIDCheck health and layout before data lands on them
Secure wipeCustomer data must not leave on returned hardware

The same ideas for virtual servers are in cloud migration with zero downtime. Choose the target in dedicated server vs cloud server and compare machines on the dedicated server page.

Frequently asked questions

Can I keep the old IP?

Usually not between machines. Plan for a new IP and update everything that depends on the old one.

How long does the copy take?

It depends on data size and link speed. Measure a sample transfer and extrapolate, then add margin.

What about email?

If mail runs on the server, move it deliberately and update rDNS and SPF. If it runs elsewhere, leave MX alone.

When can I cancel the old server?

After one to two days of clean logs and a verified backup of the new one.

dedicated migration zero downtime bare metal sofia eurovdc

EuroVDC

Full Performance, Full Control

Dedicated hardware · Root access · 99.9% uptime SLA

Rent a Dedicated Server

Did you find this content useful?

– People found it useful

Share on Social Media

Dedicated Server Migration Without Downtime